Not all remediation work requires a power interruption, and customers in locations not listed below may still benefit from work taking place in their area.
Where safe and practical, we keep the power on. However, temporary planned interruptions are sometimes required to ensure the safety of our crews, and the efficient delivery of work.
This page will provide a guide to planned work associated with our insulator pollution remediation program where a temporary power interruption may be required. The schedule is yet to be finalised and once completed, will be updated regularly. It may also change at short notice due to operational or weather conditions.
Customers directly impacted by planned outages will be informed via SMS and email. Customers can also subscribe to our notification service to stay updated on planned and unplanned outages.
Pollution Mitigation Plan (PMP) works for each region
Information for each region will be updated as it becomes available. Expand each section below to read more:
Remediation works
Insulator pollution remediation work will start on Eyre Peninsula from August.
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages to a maximum of 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
| Area |
Between the dates of |
Notes |
|---|---|---|
| Arno Bay to Cleve | 5 August - 7 August |
Single-day outage on 6 August affecting Arno Bay township and surrounds including Wharminda & Boothby. |
| Cowell to Cleve | 2 August - 5 August |
Work in rural area between Cleve and Cowell. Momentary outages to Cowell township during generator connection and disconnection. Single-day outages to Campoona, Mangalo, Elbow Hill and Mt Olinthus SWER lines. |
| Port Lincoln to Coffin Bay and Port Lincoln to Uley | 22 August - 28 August |
Six single-day outages affecting customers between Pt Lincoln, Coffin Bay and Uley South. Coffin Bay township will be supported by generators but may experience short outages when we connect and disconnect the generators. Customers at Wangary, Fountain, Wanilla, Coulta, Farm Beach and Mt Dutton Bay may experience two outages on separate days during this timeframe. |
Map of works area
Picture: Map of Pollution Mitigation Plan (PMP) works on Eyre Peninsula during 2026.
Remediation works
Insulator pollution remediation work will start on Kangaroo Island from September.
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages to a maximum of 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions. The information will be updated on an ongoing basis.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
| Area |
Between the dates of |
Notes |
|---|---|---|
| Sapphiretown to Pelican Lagoon | 21 September - 23 September |
Two short outages up to 15 minutes each in the morning and afternoon on 22 September affecting customers in Island Beach, Pelican Lagoon and Sapphiretown. |
| Kangaroo Island | 29 September - 1 October |
Two short outages up to 15 minutes each in the morning and afternoon on 30 September. These outages will affect all customers on Kangaroo Island. |
Remediation works
The schedule for remediation works on the Fleurieu Peninsula and Kangaroo Island is currently being finalised. Once confirmed, this page will be updated with the relevant information.
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
Map of works area
Picture: Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Murraylands, the Fleurieu Peninsula and the South East of SA for 2026.
Remediation works
Insulator pollution remediation work will start in the Mid North from late August.
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages to a maximum of 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
| Area |
Between the dates of |
Notes |
|---|---|---|
| Hummocks - Port Wakefield | 24 August - 27 August |
Four single-day outages affecting customers only once on different sections between Beaufort, Pt Wakefield and Wild Horse Plains. |
| Port Wakefield - Balaklava | 31 August - 3 September |
Three single-day outages affecting customers only once between Pt Wakefield, Balaklava, Everard Central and Avon. Port Wakefield single-day outage will occur on 31 August, also affecting south towards Wild Horse Plains. |
|
Ninnes - Lochiel and surrounds |
5 September - 11 September |
Two over-night outages affecting Ninnes to Lochiel and surrounding rural areas. |
| Balaklava - Whitwarta - Beaufort - Inkerman |
13 September - |
Balaklava outage on Sunday 13th September. Followed by three single-day outages affecting customers only once on different sections around Beaufort, Whitwarta, Inkerman and surrounding areas. |
Map of works area
Picture: Map of Pollution Mitigation Plan (PMP) works in the Mid North at Port Wakefield and Clare around the Hummocks area for 2026.
Remediation works
Insulator pollution remediation work will start in the Murraylands from September.
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages to a maximum of 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
| Area |
Between the dates of |
Notes |
|---|---|---|
| Meningie West to Narrung to Poltalloch (does not include Meningie town) | 7 September - 11 September |
Two day-time outages on 8 September and 10 September affecting customers in Meningie West, Narrung, Poltalloch and surrounds. |
| Coonalpyn to Meningie and the Narrung Peninsula | 15 September - 18 September | Overnight outage on 16 September affecting customers in Ashville, Colebatch, Cooke Plains, Coonalpyn, Coorong, Field, Malinong, Meningie, Meningie East, Meningie West, Narrung, Poltalloch, Salt Creek, Waltowa, Wellington East & Yumali. |
| East of Meningie town to Field (not including Meningie town) | 21 September - 25 September |
Two day-time outages on 22 and 24 September affecting separate customers East of Meningie including customers in Field, Coorong, Meningie East and including some customers just outside of Meningie town. |
| North of Meningie around Waltowa (not including Meningie town) | 22 September - 24 September | Day-time outage on 23 September affecting customers North of Meningie in and around Waltowa including some customers just outside of Meningie town. |
| Naturi to Tailem Bend to Wellington East | 17 November - 20 November | Overnight outage on 18 November affecting customers in Tailem Bend, Naturi, Wellington East & Wynarka. |
Map of works area
Picture: Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Murraylands, the Fleurieu Peninsula and the South East of SA for 2026.
Remediation works
Insulator pollution remediation work will start in Port Augusta and surrounding areas from September.
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages to a maximum of 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
| Area |
Between the dates of |
Notes |
|---|---|---|
| West side of the river in Pt Augusta and some customers in Pt Augusta (surrounding Thompson St and Innes St) to Blanche Harbor, Lincoln Gap, Pandurra and up to Lake Dutton | 18 September - 23 September |
Two nighttime outages affecting the same customers on 19 & 21 September in Pt Augusta, Pt Augusta West, Blanche Harbor, Carriewerloo, Commissariat Point, Kootaberra, Cultana, Lincoln Gap, Oakden Hills, Pandurra, Wartaka & Yudnapinna. For residential customers in Pt Augusta, there may be noise whilst working in the street. |
| Stirling North to Kanyaka (including Quorn town) | 19 September - 23 September | Two nighttime outages affecting the same customers on 20 & 22 September in Stirling North, Quorn, Pt Paterson, Bruce, Davenport, Kanyaka & Saltia. |
| Pt Augusta West to Blanche Harbor, Lincoln Gap, Pandurra and up to Lake Dutton | 2 November - 5 November |
Nighttime outage on 3 November affecting customers in Pt Augusta West, Blanche Harbor, Commissariat Point, Lincoln Gap, Cultana, Pandurra, Carriewerloo, Kootaberra, Yudnapinna, Oakden Hills & Wartaka. |
Map of works area
Picture: Map of Pollution Mitigation Plan (PMP) works around Port Augusta for 2026.
Remediation works
The schedule for remediation works in the South-East is currently being finalised. Once confirmed, this page will be updated with the relevant information.
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
Map of works area
Picture: Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Murraylands, the Fleurieu Peninsula and the South East of SA for 2026.
Remediation works
Insulator pollution remediation work will start in and around Whyalla from August.
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages to a maximum of 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
| Area |
Between the dates of |
Notes |
|---|---|---|
|
Whyalla Playford |
3 August - 4 August |
15 properties affected on 4 August around Ayliffe St Whyalla Playford. |
| False Bay, Fitzgerald Bay, Whyalla Barson, Backy Point and Douglas Point | 29 September - 1 October and 13 October - 15 October |
114 properties affected on 30 September and 14 October in False Bay, Fitzgerald Bay, Whyalla Barson, Backy Point and Douglas Point and surrounding areas. |
Map of works area
Picture: Map of Pollution Mitigation Plan (PMP) works for Whyalla and surrounds for 2026.
Remediation works
For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.
Please note that dates may change at short notice due to operational requirements or weather conditions.
In addition to the works scheduled below, there will be some additional planned outages on Yorke Peninsula to install high voltage automated switches. These switches improve the network by making it easier in an outage for crews to pinpoint the location of a fault, so that restoration can happen sooner.
Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.
| Area |
Between the dates of |
Notes |
|---|---|---|
| Kulpara to Willamulka to Wokurna to Everard Central and areas in-between (includes Lochiel & Bute) | 9 August - 9 August |
Outage on Sunday, 9 August, affecting customers in Bute, Lochiel, Kulpara, South Hummocks, Ninnes, Thomas Plain, Wokurna, Barunga Gap, Bumbunga, Everard Central, Nantawarra and surrounding rural areas. |
| Areas around Melton, Kainton and Sunnyvale | 6 September - 11 September |
Four single-day outages affecting customers no more than two times: On 7 September an outage affecting Sunnyvale, Agery, Kainton, South of Paskeville and surrounding rural areas. On 8 September an outage affecting Melton area and South West of Kulpara. On 9 September an outage affecting Sunnyvale, Agery, Kainton, South of Paskeville and surrounding rural areas. On 10 September an outage affecting Melton area and South West of Kulpara. |
| Areas around Melton, Kainton and Sunnyvale | 30 September - 2 October |
On 1 October an outage affecting Sunnyvale, Agery, Kainton, Melton and rural area between Paskeville and Kulpara. |
| North of Minlaton to Agery (including Maitland, Pt Victoria & Arthurton) | November | Two overnight outages in November affecting customers at Pt Rickaby, Koolywurtie, Wauraltee, Urania, Pt Victoria, Point Pearce, Chinaman Wells, Balgowan, Arthurton, Petersville, and surrounding rural areas. |
| Ninnes to Lochiel and surrounding rural areas | November | Two overnight outages in November affecting customers at Ninnes, Lochiel, Everard Central, Bumbunga, Barunga Gap and surrounding rural areas. |
Picture: Map of Pollution Mitigation Plan (PMP) works on the Yorke Peninsula for 2026.