Planned work - SA Power Networks Skip to content

Not all remediation work requires a power interruption, and customers in locations not listed below may still benefit from work taking place in their area.

Where safe and practical, we keep the power on. However, temporary planned interruptions are sometimes required to ensure the safety of our crews, and the efficient delivery of work.

This page will provide a guide to planned work associated with our insulator pollution remediation program where a temporary power interruption may be required. The schedule is yet to be finalised and once completed, will be updated regularly. It may also change at short notice due to operational or weather conditions.

Customers directly impacted by planned outages will be informed via SMS and email. Customers can also subscribe to our notification service to stay updated on planned and unplanned outages.

Pollution Mitigation Plan (PMP) works for each region

Information for each region will be updated as it becomes available. Expand each section below to read more:

Remediation works

Insulator pollution remediation work will start on Eyre Peninsula from August.

For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages to a maximum of 10 business days.

Please note that dates may change at short notice due to operational requirements or weather conditions.

Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.

Area

Between the dates of

Notes
Arno Bay to Cleve 2 August -
5 August
Arno Bay township and surrounds including Wharminda & Boothby – single-day outage.
Cowell to Cleve 2 August -
5 August

Work in rural area between Cleve and Cowell.

Momentary outages to Cowell township during generator connection and disconnection.

Single-day outages to Campoona, Mangalo, Elbow Hill and Mt Olinthus SWER lines.

Port Lincoln to Coffin Bay and Port Lincoln to Uley 22 August - 
28 August 

Six single-day outages affecting customers only once on different sections between Pt Lincoln, Coffin Bay and Uley South.

Coffin Bay township will be supported by generators but may experience short outages when we connect and disconnect the generators.

 

Map of works area

Map of Pollution Mitigation Plan (PMP) works on the Eyre Peninsula.

Picture: Map of Pollution Mitigation Plan (PMP) works on Eyre Peninsula during 2026.

Remediation works

The schedule for remediation works on the Fleurieu Peninsula and Kangaroo Island is currently being finalised. Once confirmed, this page will be updated with the relevant information.

For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.

Please note that dates may change at short notice due to operational requirements or weather conditions.

Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.

Map of works area

Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Fleurieu Peninsula and the South East of SA for 2026.

Picture: Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Murraylands, the Fleurieu Peninsula and the South East of SA for 2026.

Remediation works

Insulator pollution remediation work will start in the Mid North from late August.

For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages to a maximum of 10 business days.

Please note that dates may change at short notice due to operational requirements or weather conditions.

Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.

Area

Between the dates of

Notes
Hummocks - Port Wakefield 24 August -
27 August
Four single-day outages affecting customers only once on different sections between Beaufort, Pt Wakefield and Wild Horse Plains.
Port Wakefield - Balaklava 31 August - 3 September

Three single-day outages affecting customers only once between Pt Wakefield, Balaklava, Everard Central and Avon.

Port Wakefield single-day outage will occur on 31 August, also affecting south towards Wild Horse Plains.

Ninnes - Lochiel and surrounds

5 September -
11 September
Two over-night outages affecting Ninnes to Lochiel and surrounding rural areas.
Balaklava - Whitwarta - Beaufort - Inkerman

13 September - 
16 September

Balaklava outage on Sunday 13th September.

Followed by three single-day outages affecting customers only once on different sections around Beaufort, Whitwarta, Inkerman and surrounding areas.

 

Map of works area

Map of Pollution Mitigation Plan (PMP) works in the Mid North at Port Wakefield and Clare around the Hummocks area for 2026.

Picture: Map of Pollution Mitigation Plan (PMP) works in the Mid North at Port Wakefield and Clare around the Hummocks area for 2026.

Remediation works

The schedule for remediation works in the Murraylands is currently being finalised. Once confirmed, this page will be updated with the relevant information.

For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.

Please note that dates may change at short notice due to operational requirements or weather conditions.

Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.

Map of works area

Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Murraylands, the Fleurieu Peninsula and the South East of SA for 2026.

Picture: Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Murraylands, the Fleurieu Peninsula and the South East of SA for 2026.

Remediation works

The schedule for remediation works in Port Augusta and the surrounding area is currently being finalised. Once confirmed, this page will be updated with the relevant information.

For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.

Please note that dates may change at short notice due to operational requirements or weather conditions.

Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.

Map of works area

Map of Pollution Mitigation Plan (PMP) works around Port Augusta for 2026.

Picture: Map of Pollution Mitigation Plan (PMP) works around Port Augusta for 2026.

Remediation works

The schedule for remediation works in the South-East is currently being finalised. Once confirmed, this page will be updated with the relevant information.

For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.

Please note that dates may change at short notice due to operational requirements or weather conditions.

Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.

Map of works area

Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Murraylands, the Fleurieu Peninsula and the South East of SA for 2026.

Picture: Map of Pollution Mitigation Plan (PMP) works on Kangaroo Island, the Murraylands, the Fleurieu Peninsula and the South East of SA for 2026.

Remediation works

The schedule for remediation works in Whyalla and surrounding area is currently being finalised. Once confirmed, this page will be updated with the relevant information.

For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.

Please note that dates may change at short notice due to operational requirements or weather conditions.

Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.

Map of works area

Map of Pollution Mitigation Plan (PMP) works for Whyalla and surrounds for 2026.

Picture: Map of Pollution Mitigation Plan (PMP) works for Whyalla and surrounds for 2026.

Remediation works

The schedule for remediation works on Yorke Peninsula is currently being finalised. Once confirmed, this page will be updated with the relevant information.

For detailed outage information related to these works, visit our Outage Map and search for 'future outages' within 10 business days of the scheduled commencement date. The outage map only shows future outages within 10 business days.

Please note that dates may change at short notice due to operational requirements or weather conditions.

Customers directly affected by planned outages will be notified via SMS and email. If you are not already subscribed, you can sign up to receive outage notifications and stay informed about planned and unplanned outages.

Map of works area

Map of Pollution Mitigation Plan (PMP) works on the Yorke Peninsula for 2026.

Picture: Map of Pollution Mitigation Plan (PMP) works on the Yorke Peninsula for 2026.


More