5 June 2025
We are continuing upgrades to the local electricity distribution network, supplied from the East Terrace substation.
Stage one of the project is now complete, and we will continue with stage two which involves civil excavation and the installation of new 33,000 Volt (33kV) underground cables along Grenfell Street between Frome Road and East Terrace. See map for further details.
Construction activities will take place between 7am and 5pm Monday to Friday (road restrictions only 9am to 4pm).
Early enabling works began on Wednesday 4 June 2025. The main construction works start from Tuesday 10 June 2025, continuing through to late August 2025, weather permitting.
We don't expect any power interruptions for these works.
If you have any questions about our work, please contact Kyron in the Customer Communications team on 08 7326 2924.
17 April 2025
Our investigation works have been completed and we will now proceed to undertake essential maintenance on our East Terrace substation, located on East Terrace between Grenfell and Pirie Street in Adelaide. Work is scheduled between 7am and 5pm, Monday to Saturday from Monday 28 April 2025 until June 2025, with occasional Sunday work if needed.
We will minimise noise and other disruptions as much as possible however there will be noise, vibration and potential dust associated with our works. Traffic management will be in place when our crews are on site.
We do not expect any power interruptions during these works. However, we encourage anyone not already subscribed to sign up for updates using the National Meter Identifier (NMI) from their electricity bill. We send updates for both planned, and unplanned, outages (eg storms), and for projects that may have some disruption to you.
If you have any questions or require any further information regarding our work, please contact Kyron in the Customer Communications Team on (08) 7326 2924.
28 March 2025
SA Power Networks is conducting investigation works on East Terrace from Friday 28 March 2025 to Saturday 29 March 2025, with work occurring between the hours of 7am to 4pm.
These investigation works will be within the footpath along East Terrace between Grenfell Street and Pirie Street.
There will be no traffic lane closures associated with these works, but speed restrictions will be in place to ensure safety for our workers onsite. There will be pedestrian detours in place as per the below map.
Map of works
Indicative map of the area of works on East Terrace.
Grenfell Street westbound lanes - between East Terrace and Frome Street
- Day works
- June to August 2025
Grenfell Street and East Terrace intersection and East Terrace
- Day works
- June to August 2025