Helicopter inspections provide a bird’s eye view of the network to identify any obvious faults or potential defects we might miss from the ground. Not all inspections can be done by helicopter and will be patrolled from the ground if required.

Aerial patrols also form part of our annual maintenance program to inspect our powerlines and other assets in bushfire risk areas. We do this to ensure our network is safe and reliable, and meets the higher demand for power in the warmer months.

Risks we look for include:

  • vegetation close to powerlines
  • birds’ nests
  • low hanging powerlines
  • damaged equipment.
     

Using a helicopter also reduces the impact on properties as there’s no need to drive through paddocks or crops. We recommend moving livestock from paddocks with powerlines when we’re doing inspections in your area, as the helicopter may hover at low heights.


Dates of powerline inspections by helicopter

We conduct aerial inspections of powerlines across different regions of South Australia according to the schedule below. Powerline inspections via helicopter typically start from mid-May and will be completed prior to the start of the CFS fire danger season dates. Please note that dates are approximate and are subject to change.

See a map and indicative schedule for 2023 inspection dates in your region below.

Aerial inspections by helicopter map of South Australia 2023

Eyre and Upper North 

District Date*
Ceduna 2 May - 6 May
Cleve 3 July - 14 July
Cummins 7 June - 17 June
Hawker 7 August - 8 August
Port Augusta  1 August - 5 August
Port Lincoln  26 June - 30 June
Streaky Bay  10 May - 15 May
Wudinna  17 May - 31 May

 

Fleurieu and Barossa

District Date*
Gawler 19 September - 28 September
Kangaroo Island 3 October - 11 October
Mclaren Vale 2 October - 5 October
Nuriootpa 5 September - 12 September
Strathalbyn 3 October - 10 October
Victor Harbor 19 September - 28 September

 

Hills and Metro

District Date*
Gumeracha 10 October - 16 October
Metro 33/66kv 10 October - 16 October
Mount Barker 10 October - 16 October
Noarlunga 14 October - 17 October

 

Mid North

District Date*
Burra 16 May - 22 May
Clare 2 May - 13 May
Gladstone 27 June - 11 July
Kadina 18 July - 4 August
Maitland 8 August - 12 August
Port Pirie 20 June - 23 June
Riverton 27 May - 11 June
Yorketown 15 August - 28 August

 

Murrayland

District Date*
Coonalpyn 7 August - 21 August
Lameroo 21 August - 30 August
Mannum 18 September - 27 September
Murray Bridge 4 September - 13 September

 

Riverland

District Date*
Barmera 15 August - 19 August
Loxton 15 August - 24 August
Waikerie 1 September - 5 September

 

South East

District Date*
Bordertown 26 June - 13 July
Millicent 22 May - 31 May
Mount Gambier 8 May - 17 May
Naracoorte 5 June - 19 June

 

* Dates are subject to change.

Not all inspections can be done by helicopter and some areas will be patrolled from the ground if required. We may need access to your property in some instances.

 

Other ways we inspect powerlines

Powerline inspections by aerial drones

Powerline inspections by robots