This page provides updates on work taking place in areas affected by insulator pollution. Content is updated as new information becomes available. Regional updates are listed further down this page.

The table below shows our progress on insulator washing and upgrades across impacted areas.

Region Total poles to be washed Total completed % Completed
Eyre Peninsula 1196 469 39%
Kangaroo Island 24 24 100%
Lower Murray 25 25 100%
Mid North 896 369 41%
South East 128 56 44%
Upper North 207 207 100%
Lower Yorke Peninsula 1143 634 55%
Upper Yorke Peninsula 1112 417 38%
Totals 4731 2201 47%

Last Updated: 24 February 2026


Yorke Peninsula

Current activity

  • Insulator washing and targeted replacement of the most affected insulators are taking place across the region

  • Mobile generation was installed at Minlaton in February to strengthen local supply while other remediation work continues

  • Helicopter insulator washing is taking place from the first week of March

  • Ongoing inspections are underway to identify assets most at risk and prioritise further washing and replacement

Community meetings

Planned work

  • Planned work in relation to insulator pollution for the Yorke Peninsula over the next two weeks is listed on the Planned Work page.

Eyre Peninsula

Current activity

  • Insulator washing and targeted replacement of the most affected insulators are taking place across the region

  • Mobile generation was installed at Cowell in February to strengthen local supply while other remediation work continues

  • Helicopter insulator washing is taking place in March

  • Ongoing inspections are underway to identify assets most at risk and prioritise further washing and replacement

Community meetings

Planned work

  • Planned work in relation to insulator pollution for the Eyre Peninsula is listed on the Planned Work page.

Limestone Coast

Current activity

  • Insulator washing and targeted replacement of the most affected insulators are taking place across the region
  • Mobile generation is being installed at Beachport in early March
  • Ongoing inspections to identify assets most at risk and prioritise further washing and replacement

Community meetings

  • A community meeting was held in Beachport on 24 February, with information provided by SA Power Networks.

Planned work

  • Planned work in relation to insulator pollution for the Limestone Coast is listed on the Planned Work page.

Kangaroo Island

Current activity

  • Insulator washing and targeted replacement of the most affected insulators are taking place across the region

  • Backup generation is in place at Kingscote on Kangaroo Island 

  • Ongoing inspections are underway to identify assets most at risk and prioritise further washing and replacement

Planned work

  • Planned work in relation to insulator pollution for Kangaroo Island is listed on the Planned Work page.