Skip to content
Ensuring Reliable Supply for Adelaide's Eastern Suburbs - Northfield GIS Draft Project Assessment Report

Northfield Gas Insulator Switchgear (GIS) - Draft Project Assessment Report (DPAR) SA Power Networks has prepared this Draft Project Assessment Report (DPAR) in accordance with the requirements of clause 5.17.4 of the National Electricity Rules (NER). It is the second stage of the formal consultation process set out in the NER in relation to applying the RIT-D. This DPAR follows the publication by SA Power Networks of the options screening notice. SA Power Networks has concluded that there will not be a non-network option, or stand-alone power system (SAPS) option, that could form a potential credible option on a standalone basis, or that could form a significant part of a potential credible option for this RIT-D. The Closing date for submissions is 6 weeks from publication. Submissions close on 18th November.

Northfield Gas Insulator Switchgear (GIS) - Draft Project Assessment Report (DPAR) SA Power Networks has prepared this Draft Project Assessment Report (DPAR) in accordance with the requirements of clause 5.17.4 of the National Electricity Rules (NER). It is the second stage of the formal consultation process set out in the NER in relation to applying the RIT-D. This DPAR follows the publication by SA Power Networks of the options screening notice. SA Power Networks has concluded that there will not be a non-network option, or stand-alone power system (SAPS) option, that could form a potential credible option on a standalone basis, or that could form a significant part of a potential credible option for this RIT-D. The Closing date for submissions is 6 weeks from publication. Submissions close on 18th November.